Greenpeace Africa has submitted comments to Naledzi Environmental Consultants opposing Eskom’s application for postponements and suspensions from complying with South Africa’s Minimum Emission Standards (MES).

The MES are designed to improve air quality in the country.

“Greenpeace Africa is vehemently opposed to Eskom’s application for further postponements and/or suspensions from air quality legislation,” says Melita Steele, senior climate and energy campaign manager for Greenpeace Africa. “In the interests of realising our constitutional right to a healthy environment, absolutely no further postponements should be given to Eskom (or, indeed, any other entity).

“Eskom should either comply with the MES or its coal-fired power stations must be retired (at an accelerated pace) because thousands of people’s lives are on the line.”

Eskom was granted a five-year postponement from compliance in 2015, and the embattled utility is now applying for yet another set of postponements and, in some cases, complete suspensions from complying.

“While we acknowledge that Eskom is in crisis, we can no longer ignore the deadly impacts of Eskom’s dirty fleet of coal-fired power stations,” says Steele. “It is unacceptable that in Eskom’s application, the utility is significantly downplaying the health impacts and premature deaths from their coal-fired power stations.

“Eskom consistently ignores international research standards and uses outdated research, unacceptable timelines and highly exaggerated cost assumptions for retrofitting pollution abatement technology. According to international best practice, compliance with the MES is absolutely possible [4]; Eskom is simply choosing instead to seek out a new licence to kill.”

Air pollution remains a problem in South Africa, particularly in areas like the Highveld, where air quality remains poor or has further deteriorated from “potentially poor” to “poor” and is out of compliance with air quality legislation. Mpumalanga province in South Africa is the largest NO2 air pollution hotspot in the world, according to new satellite data assessed by Greenpeace for the period of 1 June to 31 August 2018.

Between April 2016 and December 2017, Eskom’s seventeen coal-fired power stations reported nearly 3 200 exceedances of their daily Atmospheric Emissions Licenses limits for particulate matter, sulfur dioxide, and oxides of nitrogen. Eskom’s ‘Emission Reduction Plan’ would allow the company to operate its entire existing fleet without controls for sulphur dioxide and mercury.

“As far as Greenpeace Africa is concerned, no further postponements or suspensions can legally be granted to the utility by the National Air Quality Officer and Eskom’s application should be dismissed,” Steele says. “We take this position given the air pollution crisis in Mpumalanga, the length of time that Eskom has had available in which to prepare to comply, the flawed application, and the thousands of premature deaths that will be caused if Eskom does not comply.

“Eskom has presented no evidence in this application or otherwise that indicates its commitment to decommissioning, which makes suspensions from complying an impossible choice. We call on Eskom to abandon its renewed attempt to avoid complying with air quality legislation that has been put in place to protect people’s health.”